ADU rules depend on where the lot sits. In Sisters, the city allows one accessory dwelling per lot, up to 800 square feet of living area. In Bend, the city allows up to two ADUs and issues one combined permit. Unincorporated Deschutes County has a separate rural process. Confirm the current rules with the office that has authority.
How can I tell which rules apply to my lot?
The first question is jurisdiction, not floor plan. A lot inside Sisters city limits follows the Sisters Development Code, section 2.15.300, and the building permit is issued by Deschutes County for the city. A lot inside Bend city limits follows the City of Bend's ADU Resource Hub and Bend Development Code 3.6.200, and the city itself issues the permit. A lot in unincorporated Deschutes County follows the county's ADU Research Checklist.
If you are inside a city, do not use the county rural checklist as your guide. If you are outside a city, do not assume Bend's or Sisters' size limits apply. We help you sort that out on the first site visit, and we still want you to confirm details with the planning office that has authority.
Private CC&Rs or an HOA can be stricter than the public code. The City of Bend says it does not enforce private covenants. Check those documents separately.
What are the ADU rules in Sisters?
Sisters Development Code 2.15.300, as published, includes these standards (always confirm the current adopted text):
- ADUs go through a Type I review and must also meet the setbacks, height, and lot coverage of the underlying zoning district.
- A maximum of one ADU is allowed per lot.
- Maximum living area is 800 square feet.
- The ADU may be detached, attached to a garage, or converted from part of the primary dwelling.
- One additional on-site parking space is required for the ADU.
- Exterior finish, roof pitch, trim, window proportion and orientation, and eaves must be the same as, or visually match, the primary dwelling.
- The entrance needs a Dark Skies-compliant light, and the ADU needs house numbers visible from the street.
- Water and sewer service to the lot has to be adequate, or the owner is responsible for upsizing or adding a lateral.
The city's Land Use Application Guide gives a rough timeline of 30 to 60 days for Type I reviews, including an ADU permit. That is the land-use step, not the building permit. As with other Sisters projects, Deschutes County issues the building permit for the city. A new detached ADU is a new dwelling or accessory structure, so Oregon's R327 wildfire home-hardening code, in effect in Sisters since April 1, 2026, likely applies. Confirm that with the building official, especially if you are converting existing space rather than building new.
The city also charges system development charges for ADUs. Use the city's current SDC worksheet rather than a figure from a blog post.
What are the ADU rules in Bend?
The City of Bend's ADU Resource Hub and code-requirements page, and Bend Development Code 3.6.200, describe a different framework:
- ADUs are allowed on a residential lot (and some commercial lots) with a single-unit home, townhome, or manufactured home, except on a lot or parcel created by a middle housing land division. The development code also says ADUs are not permitted in a cottage development.
- A maximum of two ADUs is allowed per lot or parcel.
- A single ADU may be up to 800 square feet of floor area; a second ADU on the same lot may be up to 500 square feet. The development code explains how floor area is measured, including stairs and sloped ceilings.
- A detached ADU must be at least six feet from other dwellings on the same lot, with limited exceptions (including some structures legally built before April 1, 2016).
- Height, setbacks, lot coverage, and floor-area ratio follow the zoning district.
- The city requires no minimum on-site parking for an ADU.
- You submit one permit that covers both Planning and Building Safety. The city estimates processing at 4 to 8 weeks, depending on how complete the application is and how quickly you respond to review comments.
- The city offers a free pre-approved ADU plans program. Using those plans is optional. Inside Bend city limits, the City licenses five plans that any applicant can use for permitting if they apply with the City, sign the end-user agreement, and build the plan exactly as shown. The plans are free; site-specific review, building permit, planning, and system development charges still apply. If that path fits your lot, we can build from those City plans. For more on the program, read Bend's free pre-approved ADU plans: what they cover and what they don't. We do not use the Chamber-listed Simplicity plans, which the City and Chamber describe as available to build through Simplicity.
- Special standards apply in Northwest Crossing and in historic areas. Properties on septic need a septic authorization as part of the city process.
The city does not publish a single ADU fee in the hub. Permit fees and SDCs both apply; Bend tells applicants to request estimates from Building Safety and Development Services. There is an SDC deferral program to ask about if it matters for your project.
What if the lot is in unincorporated Deschutes County?
Do not apply the Sisters or Bend city limits. The county's ADU Research Checklist is the starting point, and the county advises calling planning staff before you apply.
As of the checklist we reviewed, a rural ADU generally requires:
- A legal lot of record with a primary dwelling, in one of these zones: RR-10, MUA-10, UAR-10, SR-2½, or WTZ.
- At least two acres, or at least five acres in designated South Deschutes County areas (the county publishes a map).
- No more than 900 square feet of "useable floor area," measured as the checklist describes. An attached garage, in the county's FAQ, does not count toward that 900 square feet.
- A location no farther than 100 feet from the primary dwelling, measured as the checklist describes.
- A septic site evaluation before the land-use application. The county says those evaluations typically take about four weeks and can be delayed by winter weather.
- Other permits as they apply: planning ADU permit, onsite wastewater, driveway access, and a building permit.
The county's FAQ says rural ADUs are allowed only in rural residential exception areas, and that this does not include unincorporated communities such as Tumalo, Terrebonne, or Sunriver. The checklist's eligible zones also do not include the Resort Community Zone that covers Black Butte Ranch. Confirm any edge case with county planning rather than assuming a lot qualifies.
If a rural lot meets those county criteria, we can take on the ADU. We do not offer ADUs at Black Butte Ranch under this county program, because the Ranch is in the Resort Community Zone.
The same FAQ says that once you establish an ADU, you may not use the primary dwelling or the ADU as a vacation rental, as the county and state define that use. Long-term rental is treated differently. If short-term rental is part of your plan, ask planning before you design the building.
A newly built ADU in unincorporated Deschutes County is also subject to R327 as of April 1, 2026, because that code applies to new dwellings and new accessory structures throughout the unincorporated county. Confirm conversions with the building official.
What does Sisters Custom Homes’ ADU process look like?
Cory Kent, owner-builder at Sisters Custom Homes, Oregon CCB #260626, starts by confirming jurisdiction, zoning, and any private restrictions, then helps you decide whether an ADU, an addition, or something else is the better fit. We prepare drawings and applications and work with you through submittal to the right building department, following the same path described on our process page.
We build the ADU types allowed on the lot: detached, attached, garage conversions, and conversions of existing interior space. In Bend, we also build from the City's free pre-approved ADU plans when a lot inside city limits qualifies, following the City's process and the requirement that the plan be built exactly as shown. On eligible rural lots in unincorporated Deschutes County, we take on ADU projects that meet the county's checklist — zoning, acreage, size, siting, and a septic evaluation come first. That county program does not include Tumalo, Terrebonne, Sunriver, or the Resort Community Zone that covers Black Butte Ranch, and we do not offer ADUs at the Ranch on the basis of that program.
Our estimates are open-book. We will not guess at a cost or a construction calendar in this post. Both depend on the site, the design, utility work, and the jurisdiction.
You can read more about our ADU work, building in Sisters, and building in Bend.
FAQ
How many ADUs can I build in Sisters vs. Bend?
In Sisters, the development code allows one ADU per lot, up to 800 square feet of living area. In Bend, the city allows up to two ADUs per lot or parcel: the first up to 800 square feet, and a second up to 500 square feet. Some Bend lots, including those created by a middle housing land division, cannot have an ADU.
Who issues the building permit for an ADU in Sisters or Bend?
In Sisters, Deschutes County issues the building permit for the city, and the city handles Type I land-use review and its own fees. In Bend, the City of Bend issues one permit that covers both Planning and Building Safety.
Is parking required for an ADU?
In Sisters, yes: one additional on-site parking space for the ADU. In Bend, the city requires no minimum on-site parking for an ADU. Driveway or parking changes, if you make them, still have to meet city standards.
Can I build an ADU on a rural lot in Deschutes County?
Only if the property meets the county's rural ADU criteria, including zoning and acreage. Unincorporated communities such as Tumalo, Terrebonne, and Sunriver are called out as outside that program, and the checklist's eligible zones do not include the Resort Community Zone that covers Black Butte Ranch. If the lot qualifies, we can take on that work. We do not offer ADUs at the Ranch under this county program. Start with the county's ADU Research Checklist and talk to planning staff before you design.
Do wildfire building rules apply to a new ADU?
In Sisters and in unincorporated Deschutes County, new dwellings and new accessory structures have had to meet ORSC R327 since April 1, 2026. Ask the building official how that applies to a conversion of existing space. This post does not state a Bend R327 rule; confirm Bend requirements with the city.
Can I use the City of Bend's pre-approved ADU plans?
Yes, if the lot is inside Bend city limits and the site qualifies for the program. The City licenses five free plans for permitting use in Bend. The owner applies with the City, signs the end-user agreement, and the plan must be built exactly as shown. Permit, planning, and system development charges still apply. We will build from those City plans. Confirm the current program rules on the City's pre-approved plans page.