Building a custom home in Sisters, Oregon: who issues the permits?

A contemporary wood-and-glass mountain home with a steep gable roof and two balconies, set among snow-covered evergreen trees.

Inside Sisters city limits, Deschutes County handles building permits, plan review, and inspections under a contract with the city. The City of Sisters still oversees zoning, land use, and its own development requirements: system development charges, Dark Skies lighting, and a final site inspection. Most custom homes need approvals from both. New homes and new accessory structures must also meet Oregon's R327 wildfire code, in effect since April 1, 2026.

Who issues the building permit in Sisters?

The City of Sisters does not run its own building department. On its Building Permits page, the city says it contracts building, plumbing, mechanical, and electrical services — including plan check, permit issuance, and inspections — to the Deschutes County Building Safety Division.

That is the opposite of what some people expect, and it is worth getting straight before you design a house. A lot inside city limits still has two public offices in the process:

  • Deschutes County reviews the construction drawings and issues the building permit.
  • The City of Sisters handles city land-use items, calculates system development charges (SDCs), reviews new exterior lighting under its Dark Skies standards, and does a final site inspection when the work and site improvements are complete.

The city's page also lists a City of Sisters Building Permit & Certificate of Occupancy Acknowledgement Form, plus the materials the county requires. For a new house, the city points to a residential submittal checklist. For a residential remodel, it tells you to contact the county directly about its requirements.

What else does the city review besides the building permit?

System development charges. The city charges SDCs based on the effect a project will have on water, sewer, transportation, and parks. It publishes a calculation worksheet and a master fee schedule, and it notes that SDC rates changed effective July 1, 2026. The county has its own building-permit fees. The city says both city and county fees have to be paid before the building permit can be issued. We do not quote fee amounts here because they change; use the city's worksheet or ask a city planner and a county permit technician for an estimate on your project.

Dark Skies. All new exterior lighting has to meet the city's Dark Skies Lighting Ordinance. The city asks for lighting specifications with the application.

Trees. The city's private tree code favors keeping trees where possible. Trees proposed for removal need to be mapped on the site plan with trunk size (DBH). A city planner can tell you whether a tree is eligible for removal.

Final city inspection. When construction and site work are finished — including landscaping, Dark Skies lighting, addressing, and paving — you schedule a site inspection with the city at least 48 hours ahead. That is separate from the county's building inspections.

Review time. As of June 2025, the city said a residential building-permit review takes about 8 to 10 weeks, and longer for multifamily or commercial projects. That figure may have changed, and it is only the public review window, not the full time to design, permit, and build a house.

If your lot is just outside city limits, the city process above does not apply. Unincorporated Deschutes County is then the permitting office, and the county's R327 rules still apply to new homes. If the lot is in Camp Sherman, permits go through Jefferson County Community Development, not Deschutes County and not the City of Sisters.

What does the R327 wildfire code mean for a new home in Sisters?

On April 1, 2026, both Deschutes County and the City of Sisters put Oregon Residential Specialty Code section R327 — wildfire hazard mitigation, often called fire hardening — into effect for new dwellings and new accessory structures. The city's building-permits page states the Sisters rule. The county's Fire Hardening Requirements (R327) page states where it applies and what it covers.

According to that county page:

  • The rules apply in all of unincorporated Deschutes County and inside Sisters city limits.
  • They apply to structures governed by the Oregon Residential Specialty Code: all newly constructed dwellings and all newly constructed accessory structures.
  • They do not apply to remodels or additions, partial repairs, manufactured dwellings (which are built to the federal HUD standard), or non-habitable detached accessory structures under 400 square feet with a roof no taller than 15 feet.
  • Fire hardening means using materials and details that make a house more resistant to embers, heat, and flame. It does not make a house fireproof.

The county notes that many of the materials already common in this area can meet the standard — for example, double-pane windows, cementitious siding, and Class B or better asphalt shingles — and that it will accept products on the CalFire building-materials lists when those products are specifically shown on the drawings. The official page is the place to check current product guidance, not a blog post.

If you are remodeling or adding on to an existing house in Sisters, R327 as adopted here is not required for that work. A brand-new house, or a newly built accessory structure, is a different matter. When in doubt, ask the county building official about your specific scope.

What does Sisters Custom Homes’ process look like?

Cory Kent, owner-builder at Sisters Custom Homes, Oregon CCB #260626, stays involved from the first conversation through construction. We start with a consultation: what you want to build, how you live, the lot, and a realistic budget. Then we work through design and planning — scope, materials, and a set of drawings and applications that can go to the right offices.

We prepare those drawings and applications and work with you through submittal. The permit itself still runs through Deschutes County, with the city steps described above. We will tell you which jurisdiction applies once we know the site. Our estimates are open-book: we show costs, markups, and profit rather than hiding behind a lump-sum number.

We do not publish a standard number of months for a Sisters custom home. Design, permitting, site work, weather, and the house itself all affect the calendar. We will talk through timing once we understand the project.

You can read more about custom homes, our process, and building in Sisters.

FAQ

Who issues building permits in Sisters, Oregon?

Inside city limits, Deschutes County's Building Safety Division reviews plans and issues the building permit under a contract with the City of Sisters. The city handles land use, system development charges, Dark Skies lighting, and a final site inspection.

Do new homes in Sisters have to meet wildfire building rules?

Yes. Since April 1, 2026, new dwellings and new accessory structures inside Sisters city limits — and in unincorporated Deschutes County — must meet Oregon Residential Specialty Code section R327. The county says remodels and additions are not included.

How long does a building permit take in Sisters?

The City of Sisters said, as of June 2025, that residential building-permit review takes about 8 to 10 weeks, and longer for multifamily or commercial work. Confirm the current estimate with the city and the county. That window is only the permit review, not the full design and construction schedule.

Do I still work with the City of Sisters if the county issues the permit?

Yes. You will still have city paperwork, city fees (including SDCs), Dark Skies lighting review, and a final city site inspection, in addition to the county building permit and inspections.

What if my lot is in Camp Sherman, not Sisters?

Camp Sherman is in Jefferson County. Building permits go through Jefferson County Community Development, not Deschutes County and not the City of Sisters.

Talk with us

If you are considering a custom home in Sisters or nearby, start with a consultation or call 541-588-0162. Cory and Nikki Kent are glad to walk a lot with you and help you sort out which office has authority before design goes too far.

Have a lot, a plan, or just an idea?

Call us at 541-588-0162 or email hello@sisterscustomhomes.com.